By using this site, you agree to the Privacy Policy and Terms of Use.
Accept
SO KONNECTSO KONNECTSO KONNECT
Notification Show More
Font ResizerAa
  • Home
  • Entertainment
  • News
  • Music
  • Sports
  • Business
  • Politics
Reading: Eskom imposes stage 6 load shedding earlier until further notice
Share
Font ResizerAa
SO KONNECTSO KONNECT
  • Home
  • Entertainment
  • News
  • Music
  • Sports
  • Business
  • Politics
Search
  • Home
  • Entertainment
  • News
  • Music
  • Sports
  • Business
  • Politics
Have an existing account? Sign In
Follow US
© Sokonnect News Network.. All Rights Reserved.
Home » Blog » Eskom imposes stage 6 load shedding earlier until further notice
News

Eskom imposes stage 6 load shedding earlier until further notice

sokonnect
Last updated: January 11, 2023 1:26 pm
sokonnect Published January 11, 2023
Share
SHARE

Contents
Generation capacityBreakdownsPlanned maintenanceRamaphosa: ANC’s top priority is to end load shedding



Ailing state-owned parastatal Eskom has warned that continuous stage 6 load shedding will be implemented from 4 pm on Wednesday, until further notice.

The power utility said the higher stage of the deliberate power cuts is necessary due to the severe capacity constraints.

Generation capacity

Eskom spokesperson Sikonathi Mantshantsha said generation capacity has to be limited.

“Eskom will continue to manage the limited emergency generation reserves to supplement generation capacity. Eskom will publish a further update as soon as there are any significant changes.”

Breakdowns

Mantshantsha said there have been a number of breakdowns which has necessitated the higher load shedding stages.

“Eleven generators amounting to 5 084MW of capacity suffered breakdowns since Tuesday morning, further reducing available capacity and necessitating the increase in the stages of load shedding.

“These were a unit each at the Camden, Duvha, Grootvlei, Hendrina, Kendal, and two units each at Kriel, Majuba and Matla power stations,”

A unit each at Camden, Duvha, Hendrina, Kriel, Matimba and Matla power stations have returned to service, representing 2 540MW of capacity,” Mantshatsha said.

ALSO READ: Ramaphosa: ANC’s top priority is to end load shedding

Planned maintenance

Mantshantsha said planned maintenance is currently 5 739MW, while breakdowns amount to 18 041MW of capacity.

“Eskom requests the public to reduce the usage of electricity and to exercise patience and tolerance during this difficult period.”

“Load shedding is implemented only as a last resort in view of the shortage of generation capacity and the need to attend to breakdowns,” he said.

Ramaphosa: ANC’s top priority is to end load shedding

Meanwhile, ass the country continues to suffer from excruciating and deliberate load shedding, African National Congress (ANC) President Cyril Ramaphosa vowed to end the rolling blackouts.

South Africa has so far experienced more than 230 days of load shedding with January 2022 the only month without any blackouts as failing state-owned entity Eskom battles to keep the lights on.

The parastatal has warned South Africans will have to work around the deliberate power cuts until further notice.

ALSO READ: South Africa is dying Mr. President, what are you doing about it?

TAGGED:earlierEskomImposesLoadnoticesheddingstage
Share This Article
Facebook Twitter Whatsapp Whatsapp Email Print
Leave a comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

© Sokonnect News Network.. All Rights Reserved.
Welcome Back!

Sign in to your account

Lost your password?